We built a raw water pipeline from our bore in Glenfern Road to the nearby Romsey Water Filtration Plant to transfer water between Romsey and Lancefield.

Project snapshot

Town(s): Romsey, 

Status: Complete

Cost: $350,000

Expected Completion Date: Completed October 2016


Why was this project needed?

We built the new raw water transfer pipeline from our bore to our water filtration plant, enabling us to transfer local water supplies more efficiently between Romsey and Lancefield.

What did the works involve?

Western Water constructed a 1.1km raw water pipeline along the roadside from our bore on Glenfern Road to the Romsey Water Filtration Plant.

Project updates

Romsey borefield update: February 2018513KB

Project update: August 2016296KB